May 2006
Final stages of construction continued along with
systems commissioning. TI is maintaining a small staff on-site
until the company decides to equip the building for operation.
March
2006
Construction completion was still set for early second
quarter of 2006. Landscaping and other external finishing
touches continued. Acceptance testing, inspections and punch
listing of new installations continued. TI closely watched
market demand to decide when the fab would become operational.
February 2006
Trailers were removed to make room for final grading
and landscaping. Roofing was completed and interior finish
work progressed as planned, along with completion of mechanical
and electrical systems. The expected completion date was set
for early in the second quarter of 2006.
January
2006
Major completion activity continued including roofing,
interior finish out work and mechanical and electrical utility
systems. Landscaping began to shape. We were still on target
for the building to be near completion at the end of the first
quarter.
|