IEC 62116 titled "Utility-Interconnected Photovoltaic Inverters – Test Procedure of Islanding Prevention Measures," defines a standardized and repeatable procedure for evaluating the anti-islanding performance of photovoltaic (PV) inverters. An equipment that meets the requirements of IEC 62116 can be classified as non-islanding, meaning it is capable of detecting an islanding condition and promptly ceasing to energize the grid under all applicable operating conditions. This section describes the test setup and methodology defined by the standard.
Test Circuit and
Components
The IEC 62116 test circuit simulates real-world grid conditions with
precise control over power flow and load balance. Its primary goal is to replicate the
worst-case scenario for anti-islanding detection, where the inverter's output closely
matches the connected load.
Key
Components:
- EUT (Equipment Under Test):
Typically a PV inverter, connected between a DC source and an AC source
representing the grid
- Adjustable RLC load network:
Connected in parallel on the AC side, allowing fine-tuned load balancing
- Measuring instruments to monitor
voltage, current, and power flow in real time
An example of the test setup with
TIDA-010938 can be seen in Figure 3-1.
What the Setup Enables:
- Simulation of balanced and
imbalanced power conditions
- Controlled grid switching
(simulating grid disconnection)
- Monitoring of the inverter's
islanding detection response time
Test Procedure
IEC 62116
provides a standardized method to evaluate anti-islanding performance in PV inverters
across three output power conditions:
- Condition A: Maximum output
- Condition B: 50–66% of
maximum
- Condition C: 25–33% of
maximum
This can be seen in Table 3-1.
Table 3-1 Trial Conditions
| Trial |
Inverter Output
Power |
Inverter Input Voltage
(VDC) |
Shutdown
Settings |
| A |
Nominal |
>90% Nominal |
Nominal V & f
shutdown |
| B |
50-66% Nominal |
50% Nominal,
+/-10% |
Nominal V & f
shutdown |
| C |
25-33% Nominal |
<10% Nominal |
Nominal V & f
shutdown |
- The test uses an RLC load tuned
to a quality factor of Qf = 1.0 +/- 0.05, simulating the worst-case
balanced island. The load is balanced so that current through the grid switch
S1 is 0 A (+/-1% rated current), representing a perfect power
match between inverter output and local load. The islanding test is triggered by
opening S1, and the run-on time is recorded until the inverter output
current is zero.
- Load imbalances are then applied
across the test conditions defined by the standard. This includes varying the
active load and/or one reactive component (either L or C); the test is repeated
after each adjustment, and the run-on time is recorded. Detailed information
regarding the test conditions for power unbalance for Trials A, B and C can be
found in the IEC-62116 standard.
- Pass/Fail Criterion: Run-on
time< 2 seconds for all tested conditions.
To evaluate the anti-islanding
performance under demanding operating conditions, the TIDA-010938 was tested against
the worst-case scenarios defined by IEC 62116 for Trials A, B, and C, without load
imbalancing. The detailed test results and analysis are provided in the design guide.