SNLA293 May   2022 DP83TC811R-Q1 , DP83TC811S-Q1

 

  1.   Trademarks
  2. 1Introduction
  3. 2Hardware Configuration
    1. 2.1 Schematic
  4. 3Software Configuration
  5. 4Testing PMA
    1. 4.1 PMA Testing Procedure
  6. 5Testing IOP: Link-up and Link-down
    1. 5.1 IOP Testing Procedure
  7. 6Testing SQI
    1. 6.1 SQI Testing Procedure
    2. 6.2 SQI Mapping with Link Quality
  8. 7Testing TDR
    1. 7.1 TDR Testing Procedure
  9. 8Testing EMC/EMI
  10. 9Revision History

Testing IOP: Link-up and Link-down

OA TC1 specifies different PHY level tests to test link-up time, link-down time and link stability. Similar ECU level tests have been highlighted in OA TC8. This section highlights the test sequence used for these IOP tests for PHY level testing and the same can be ported for ECU level tests.

TC1-interoperability tests are carried out by OA compliance test house C&S. To test interoperability of DP83TC811, C&S tests each of these parameters with DP83TC811 and other 100Base-T1 certified PHYs as its link-partners. Each of these parameters are tested for large number of iterations over different temperatures and cable lengths.