SBASAX3B May 2025 – April 2026 ADS9326 , ADS9327
PRODUCTION DATA
| PARAMETER | TEST CONDITIONS | MIN | MAX | UNIT | |
|---|---|---|---|---|---|
| CONVERSION CYCLE | |||||
| tCONV | ADC conversion time | ADS9327 | 130 | ns | |
| ADS9326 | 200 | ||||
| RESET | |||||
| tPU | Power-up time for device | 130 | ms | ||
| SPI INTERFACE TIMINGS | |||||
| tden_CSDO | Time delay: CS falling edge to data valid on SDO | 16 | ns | ||
| tdz_CSDO | Time delay: CS rising edge to SDO going Hi-Z | 7.5 | ns | ||
| tht_CKDO | Hold time: SCLK launch edge to previous data valid on SDO | 7.6 | ns | ||
| td_CKDO | Time delay: SCLK launch edge to corresponding data valid on SDO | 17 | ns | ||
| tECHO | Time delay: SCLK launch edge to SCLK echo output on D0 in SCLK Echo mode | td_CKDO – 2 | ns | ||