6.10.2.7 Independent MCU and Main Domains Power- Down
Sequencing - Option 2
Figure 6-5 describes the device power-down
sequencing for option 2.
A. Time stamp markers: T0 – MCU_PORz and PORz assert low to put all
processor resources in safe state. (0ms) T1 – All power supplies
start ramp-down. (1μs)
B. MCU_PORz and PORz must be asserted low for TΔ1 =
200μs min to ensure SoC resources enter into safe
state before any voltage begins to ramp
down.
Figure 6-8 Independent MCU and Main
Domains, Primary Power- Down Sequencing - Option
2